Log extra welder hours, crane rentals, and equipment costs for immediate superintendent sign-off.
No credit card required. Generate in 30 seconds.
The structural engineer revising connection details, requiring extensive field welding instead of bolting.
| Description of Extra Work | Labor | Materials | Total |
|---|---|---|---|
| Additional field welding per revised RFI structural details (12 hours) | Labor: $1200 | Mat: $300 | Total: $1500 |
| Extend crane rental by 1 day due to out-of-sequence delivery | Labor: $0 | Mat: $1800 | Total: $1800 |
Original Contract: $115000
This Change Order: +$3300
New Contract Total: $118300
Schedule Impact: +2 Working Days
Yes. If the foundation isn't ready or trucks are delayed, a daily rate change order must be issued.
Submit a change order for the engineering redesign and the extra fabrication required to make the beams fit.