Stop work, calculate the wasted materials, and get a signature on the spot for veneer pattern changes.
No credit card required. Generate in 30 seconds.
The architect changing the brick veneer pattern or mortar color halfway through the wall.
| Description of Extra Work | Labor | Materials | Total |
|---|---|---|---|
| Tear down and rebuild 150 sq ft of brick veneer due to color change | Labor: $900 | Mat: $450 | Total: $1350 |
| Upgrade mortar joints from standard concave to grapevine profile | Labor: $400 | Mat: $0 | Total: $400 |
Original Contract: $24000
This Change Order: +$1750
New Contract Total: $25750
Schedule Impact: +2 Working Days
Yes. If the schedule shifts into winter due to owner delays, charge for ground heaters and thermal blankets.
Issue a zero-dollar schedule change order extending your completion date, plus equipment rental overages.
We have specialized change order forms for Plumbing, Electrical, Roofing, and 20+ other construction trades.
View All 25+ Trade Templates →Join smart contractors who have ditched Excel. Lock in client approvals and protect your margins in under 30 seconds straight from your phone.