Prove unforeseen site conditions and add heavy breaker equipment costs legally.
No credit card required. Generate in 30 seconds.
Hitting solid bedrock or buried debris when you only quoted for standard soil removal.
| Description of Extra Work | Labor | Materials | Total |
|---|---|---|---|
| Hydraulic breaker rental for bedrock removal (8 hours) | Labor: $800 | Mat: $600 | Total: $1400 |
| Haul away 3 loads of unexpected buried concrete debris | Labor: $450 | Mat: $300 | Total: $750 |
Original Contract: $18000
This Change Order: +$2150
New Contract Total: $20150
Schedule Impact: +2 Working Days
Anything below ground that was not disclosed in the original soil report, like bedrock, old foundations, or high water tables.
If diesel prices spike significantly beyond contract provisions, a fuel escalation change order may be submitted.