Instantly halt standard work, document hazardous removal costs, and get client authorization.
No credit card required. Generate in 30 seconds.
Discovering hidden asbestos or hazardous materials that require special handling and disposal fees.
| Description of Extra Work | Labor | Materials | Total |
|---|---|---|---|
| Asbestos testing and abatement coordination for flooring tiles | Labor: $600 | Mat: $450 | Total: $1050 |
| Extra dumpster fees for unexpected structural steel removal | Labor: $200 | Mat: $400 | Total: $600 |
Original Contract: $12500
This Change Order: +$1650
New Contract Total: $14150
Schedule Impact: +3 Working Days
Work must stop immediately by law. A change order is issued for abatement, which often requires specialized third-party teams.
Yes, if the debris volume exceeds the original visual estimate due to hidden layers (e.g., three layers of roofing under one).
We have specialized change order forms for Plumbing, Electrical, Roofing, and 20+ other construction trades.