Get GCs and landlords to sign off on jobsite directives, out-of-sequence work, and trade delays.
No credit card required. Generate in 30 seconds.
The landlord or fire inspector requiring a different ceiling grid or lighting system than originally spec'd.
| Description of Extra Work | Labor | Materials | Total |
|---|---|---|---|
| Premium overtime labor authorization for Saturday crew to recover schedule | Labor: $2200 | Mat: $0 | Total: $2200 |
| Reroute conduit runs per RFI-042 architectural revision | Labor: $850 | Mat: $420 | Total: $1270 |
Original Contract: $85000
This Change Order: +$3470
New Contract Total: $88470
Schedule Impact: +0 Working Days
A Change Order Request (COR) proposes the cost. Once signed by the GC and Owner, it becomes a binding Change Order (CO).
Never perform extra work on a commercial site without a signed directive. Verbal promises are rarely paid by corporate owners.
We have specialized change order forms for Plumbing, Electrical, Roofing, and 20+ other construction trades.
View All 25+ Trade Templates →Join smart contractors who have ditched Excel. Lock in client approvals and protect your margins in under 30 seconds straight from your phone.