Update material tonnage and trucking costs directly from the site and get the GC to sign off.
No credit card required. Generate in 30 seconds.
Subgrade failure requiring unexpected undercutting and tons of extra stone base before paving.
| Description of Extra Work | Labor | Materials | Total |
|---|---|---|---|
| Undercut soft subgrade by 6 inches and add crushed stone base | Labor: $800 | Mat: $1200 | Total: $2000 |
| Apply extra tack coat layer due to dusty site conditions | Labor: $150 | Mat: $200 | Total: $350 |
Original Contract: $24000
This Change Order: +$2350
New Contract Total: $26350
Schedule Impact: +1 Working Days
Use an asphalt index clause. If oil prices rise, issue a material escalation change order prior to paving.
Do not pave over it. Submit a change order for the required base remediation work.